satabdi.db
|
 |
« on: September 04, 2011, 12:04:19 pm » |
|
I have a ticket in which the customer says :
He has set up PM's in Maximo that are supposed to get generated every 2000 Hours. What is happening is the work orders are generating every week, not just when the hour meter reaches 2000 more than when the PM was last generated. The customer has PM's that are set up using the Meter for the trigger to generate the PM. The PM's are generating every week instead of only when the meter reading reaches the trigger level.
Please let me know how I can resolve this issue .
|